Festival Park
Status:
- Groundbreaking ceremony held on July 26, 2024
- Park construction is 90% complete
- Anticipated to open mid 2026

April 2026 Update
- Groundbreaking: 7/26/2024
- NTP: 7/1/2024
- Contract Duration: 480 days
- Scheduled Completion: June 2026
- Construction is 90% Complete