STATUS: This park is under construction and is expected to open in the spring of 2025.

February 2024 Update
City Council agreed to Resolution 46-24 on February 7, 2024, approving a contract with Pavement Maintenance LLC to construct Crystal Lake Park in NW Cape Coral. Park amenities include a multi-use path, beach, scuba diving area, hill overlook, boat ramp, and kayak launch to Flagstone Canal, which connects to the North Spreader Waterway. The Groundbreaking Ceremony was held on February 23, 2024.
Crystal Lake Park - 2.28.24


Site Plan with Added Amenities 
Crystal Lake Park Final

Kids Fitness Playground Plans & Renderings
Crystal Lake Park_2D_T

Crystal Lake Park - Kids Fitness Playground front - Copy

Crystal Lake Park - Kids Fitness Playground side - Copy


October 2023 Update
Crystal Lake Park

FINAL Site Plan  (Rev. July 2022)
Crystal Lake Park Site Plan Final

Updated Site Plan  
Crystal Lake

Original Concept Plan  
Crystal Lake - Concept Plans
Crystal Lake - Bird's Eye View