Six Lane Improvement Project

See More City Projects >>

Project Location: Cape Coral Parkway East between Triton Court East and Cape Coral Street/SE 15th Avenue

See here for a map of work locations

Description: The Cape Coral Parkway East six-laning project is a roughly $2.3 million construction effort to add capacity and smooth traffic flow on Cape Coral Parkway. This will be achieved mainly by resurfacing and restriping to six lanes between Triton Court East and just west of Cape Coral Street/SE 15th Avenue. The project will expand Cape Coral Parkway East to six continuous lanes between Coronado Parkway and Del Prado Boulevard, improving traffic flow, resurfacing the roadway, and upgrading signals.

While there has been some discussion about potential parking losses, the CRA district is adding spaces through several strategic initiatives. With the completion of The Cove at 47th and Bimini Square parking garages, and new lots underway along Vincennes Street and Boulevard, South Cape will have more than 300 new parking spaces this year. These improvements support continued growth, better access, and a stronger South Cape for residents, visitors, and businesses alike.

Timeline

October 2026

The Cape Coral Parkway East Six Lane Improvement Project reached a major milestone, with three through lanes in each direction opened to open to traffic between Coronado Parkway and Del Prado Boulevard on October 23, 2026. Motorists should expect congestion in the area as construction continues toward the project's anticipated completion in November 2026.

May 2026

Lane closures will begin the week of Monday, May 11, on Cape Coral Parkway East between SE 15th Avenue/Cape Coral Street and Coronado Boulevard as part of the City’s Six Lane Improvement Project.

Click for more information on lane closures

April 2026

At the April 1 City Council meeting, Council approved the Cape Coral Parkway East Six‑Lane Improvement Project, a $2.37 million investment that will keep traffic in the South Cape moving safely and efficiently.