Bridge Rehabilitation Program

Bridge Rehab -1Bridge Rehab - 2Bridge Rehab - 3

Project Location: Various locations throughout the City

Project Description: Inspection and Prioritization for 140 Bridge Rehab or Replacements as needed

  • Volkert selected for Engineering Services
    • Report is currently being updated to incorporate all new post-storm inspections resulting from Hurricane Ian. Volkert is working on incorporating City issued comments on Master Plan report and recommendations. Repair recommendations, cost estimates, and program budgeting are being updated to reflect all updates,
    • Volkert will develop GIS database to populate the City's bridge inventory database and will continue to work with City GIS staff to develop database.
  • Currently 80% complete 
  • $1 Million per year budgeted for construction